Unit Rate Contract (Item Rate)

A contract that pays the contractor an agreed rate for each unit of work, so the final cost follows the quantities actually measured.

Last updated

What is Unit Rate Contract (Item Rate)?

A Unit Rate Contract, also called an Item Rate Contract, is the most common form of construction contract in India. The client does not agree one lump-sum price for the whole building. It agrees a rate for each item, for example ₹5,000 per cu.m of concrete and ₹60 per kg of steel, and the final cost follows the quantities measured on site.

Practical example

A developer signs an item rate contract for earthwork at ₹300 per cu.m. The BOQ estimated 1,000 cu.m, a budget of ₹3,00,000. During excavation the contractor hits hard rock, has to dig wider and ends up excavating 1,200 cu.m. Under the contract the developer pays ₹3,60,000 (1,200 × ₹300).

In SuperWise

In SuperWise each work order line ties a BOQ item to a contracted quantity and a contracted rate, and RA bill lines take their quantities from approved measurement sheets. The cumulative billed quantity of a line cannot pass its contracted quantity. A change in scope or rate after approval is made by amending the work order, which raises its revision number.